In the site survey of a four-sided traverse, internal angles are essential to ensure geometric accuracy. The survey revealed that the sum of the measured internal angles was 359 degrees and 48 minutes, which is 12 minutes less than the expected 360 degrees. This discrepancy signals an error likely arising from measurement inaccuracies during the fieldwork.

To rectify this error, the adjustment process involved distributing the 12-minute shortfall equally across the four internal angles. By adding three minutes to each angle, the corrected values were recalculated. The adjusted sum confirmed the accuracy of the traverse with a total of 360 degrees, ensuring that the traverse conforms to geometric principles.

Following this correction, the bearings of the traverse sides were computed. The magnetic bearing of side AB was used as the reference starting point. Using the corrected internal angles, the bearings for the remaining sides were systematically determined. This process ensures that the angular and linear relationships between all sides are accurately aligned, which is critical for precise plotting and mapping.

This method rectifies potential errors and highlights the importance of careful measurement and error adjustment in field surveys, reinforcing the accuracy and reliability of the resulting data.

Tags

Traverse AdjustmentInternal AnglesGeometric AccuracyMeasurement InaccuraciesError RectificationAngle DistributionCorrected ValuesBearings ComputationMagnetic BearingAngular RelationshipsLinear RelationshipsPlotting And Mapping AccuracyField SurveysData Reliability

来自章节 27:

article

Now Playing

27.1 : Adjusting a Traverse

Traverse and Topographic Surveying

37 Views

article

27.2 : Latitudes and Departures

Traverse and Topographic Surveying

27 Views

article

27.3 : Area Computation by the Alternative Coordinate Method

Traverse and Topographic Surveying

37 Views

article

27.4 : Areas Within Irregular Boundaries

Traverse and Topographic Surveying

54 Views

article

27.5 : Design Example: Marking Boundaries of a Site Using a Compass

Traverse and Topographic Surveying

25 Views

article

27.6 : Topographic Surveying and Contours

Traverse and Topographic Surveying

36 Views

article

27.7 : Plotting of Topographic Maps

Traverse and Topographic Surveying

28 Views

article

27.8 : Methods of Obtaining Topography

Traverse and Topographic Surveying

32 Views

article

27.9 : Design Example: Analyzing Capacity Contours for Flood Risk Assessment

Traverse and Topographic Surveying

31 Views

JoVE Logo

政策

使用条款

隐私

科研

教育

关于 JoVE

版权所属 © 2025 MyJoVE 公司版权所有,本公司不涉及任何医疗业务和医疗服务。