In the site survey of a four-sided traverse, internal angles are essential to ensure geometric accuracy. The survey revealed that the sum of the measured internal angles was 359 degrees and 48 minutes, which is 12 minutes less than the expected 360 degrees. This discrepancy signals an error likely arising from measurement inaccuracies during the fieldwork.

To rectify this error, the adjustment process involved distributing the 12-minute shortfall equally across the four internal angles. By adding three minutes to each angle, the corrected values were recalculated. The adjusted sum confirmed the accuracy of the traverse with a total of 360 degrees, ensuring that the traverse conforms to geometric principles.

Following this correction, the bearings of the traverse sides were computed. The magnetic bearing of side AB was used as the reference starting point. Using the corrected internal angles, the bearings for the remaining sides were systematically determined. This process ensures that the angular and linear relationships between all sides are accurately aligned, which is critical for precise plotting and mapping.

This method rectifies potential errors and highlights the importance of careful measurement and error adjustment in field surveys, reinforcing the accuracy and reliability of the resulting data.

Del capítulo 27:

article

Now Playing

27.1 : Adjusting a Traverse

Traverse and Topographic Surveying

24 Vistas

article

27.2 : Latitudes and Departures

Traverse and Topographic Surveying

12 Vistas

article

27.3 : Area Computation by the Alternative Coordinate Method

Traverse and Topographic Surveying

18 Vistas

article

27.4 : Areas Within Irregular Boundaries

Traverse and Topographic Surveying

38 Vistas

article

27.5 : Design Example: Marking Boundaries of a Site Using a Compass

Traverse and Topographic Surveying

15 Vistas

article

27.6 : Topographic Surveying and Contours

Traverse and Topographic Surveying

13 Vistas

article

27.7 : Plotting of Topographic Maps

Traverse and Topographic Surveying

15 Vistas

article

27.8 : Methods of Obtaining Topography

Traverse and Topographic Surveying

13 Vistas

article

27.9 : Design Example: Analyzing Capacity Contours for Flood Risk Assessment

Traverse and Topographic Surveying

24 Vistas

JoVE Logo

Privacidad

Condiciones de uso

Políticas

Investigación

Educación

ACERCA DE JoVE

Copyright © 2025 MyJoVE Corporation. Todos los derechos reservados